Construction of 5.00L.L. O.H.S.R. Providing Balance FHTCs, at Thoppilpara, Renovation of Pochakkonam Chira, Providing and Fixing Pressure Filter, Pumping Main and Interconnections in Ezhukone for improving water supply in Ezhukone Grama Panchayat (Balance Work )
| Project |
Construction of 5.00L.L. O.H.S.R. Providing Balance FHTCs, at Thoppilpara, Renovation of Pochakkonam Chira, Providing and Fixing Pressure Filter, Pumping Main and Interconnections in Ezhukone for improving water supply in Ezhukone Grama Panchayat (Balance Work ) |
| Project Code |
KLMJJM082315467 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
Construction of 5.00L.L. O.H.S.R. Providing Balance FHTCs, at Thoppilpara, Renovation of Pochakkonam Chira, Providing and Fixing Pressure Filter, Pumping Main and Interconnections in Ezhukone for improving water supply in Ezhukone Grama Panchayat (Balance Work ) |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Kottarakkara PH Dn |
| AS Amount (Rs) |
210640000
|
| AS Number |
541/2020/WRD |
| TS Amount (Rs) |
26499000 |
| TS Number |
9098/2023-2024 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
|
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| No Packages has been added for this project. |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 23 Oct 2026 |
plastering |
Kottarakkara PH Sn - AE |
|
| 21 Oct 2026 |
plastering |
Kottarakkara PH Sn - AE |
|
| 19 Oct 2026 |
plastering |
Kottarakkara PH Sn - AE |
|
| 17 Oct 2026 |
plastering |
Kottarakkara PH Sn - AE |
|
| 15 Oct 2026 |
plastering |
Kottarakkara PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
02/11/2023 |
| Scheduled date of Completion of the Project |
01 Nov 2024 |
| Expected date of Completion |
01/11/2024 |
Processing Dates
| AS Date |
21 Aug 2020 |
| TS Date |
16 Jul 2023 |