Project | WSS to Ambalappara panchayath in Ottappalam Taluk-Phase 1 |
---|---|
Project Code | PKDKIIFB0117643P1 |
Type | Package |
Main Project | WSS to Ambalappara panchayath in Ottappalam Taluk |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | 1. Construction of Pump house 2. Construction of 8.50 LL OHSR for low level 3. CWPMains (i) 350mm DI K9-7000m (ii)300mm DI K9 -300m (iii)150mm DI K9-1305m (iv) 250mm DIK9-500m 4. Dist Main-300mm DI K9 - 1305m 5. Pump set |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 100000000 |
TS Number | KWA/CE/NR/39/11-17 |
Technical specification | Construction of 8.5 LL OHSR, Laying Pumping main |
Contractor | Binumathew (Mob: 9446462010) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/08/2017 |
---|---|
Scheduled date of Completion as per agreement | 30 Dec 2018 |
Expected date of Completion | 02/12/2019 |
TS Date | 19 Jan 2017 |
---|---|
Estimate Approval | 19 Jan 2017 |
NIT Approval | 12 Jun 2021 |
Tender Closing | 07 Apr 2017 |
Technichal Pre-Qualification | 11 Apr 2017 |
Price bid opening | 11 Apr 2017 |
Workorder Date | 15 Jun 2017 |
---|---|
NA | 19 Aug 2017 |
Palakkad Project Dn AE |
Date: 02/10/2021 |
Work has been completed | 100% Completed
Phase 1 of this project completed and commissioned.