AMRUT-Improvements to Thiruvananthapuram Sewerage Scheme-Supplying and laying 600mm DI pumping main from Pump house at Edathara to STP at Muttathara-NH crossing near Lords hospital by HDD method
Project |
AMRUT-Improvements to Thiruvananthapuram Sewerage Scheme-Supplying and laying 600mm DI pumping main from Pump house at Edathara to STP at Muttathara-NH crossing near Lords hospital by HDD method |
Project Code |
TVMAMRUT021713974 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
NH Crossing |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
172900000
|
AS Number |
G O R (t). No. 534/2017/LSGD |
TS Amount (Rs) |
25000000 |
TS Number |
TS/2021-22/2022/1232 |
Total Bill Submitted (Rs) |
4816000 |
Total Bill Paid (Rs) |
4816000 |
Population Benefitted |
127 |
Capacity in MLD |
25.00 |
Actual Project Completion Date |
31 May 2023 |
Coverage |
20000 |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-Improvements to Thiruvananthapuram Sewerage Scheme-Supplying and laying 600mm DI pumping main from Pump house at Edathara to STP at Muttathara-NH crossing near Lords hospital by HDD method |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Apr 2024 |
Work restarted on 03.04.2024. Reaming works progressing at site |
Thiruvananthapuram Project AE7 |
|
26 Apr 2024 |
Work restarted on 03.04.2024. Reaming works progressing at site |
Thiruvananthapuram Project AE7 |
|
23 Apr 2024 |
Work restarted on 03.04.2024. Reaming works progress, today no work |
Thiruvananthapuram Project AE7 |
|
18 Apr 2024 |
Work restarted on 03.04.2024. Reaming works and shoring works ongoing at site |
Thiruvananthapuram Project AE7 |
|
12 Apr 2024 |
Work restarted on 03.04.2024. Reaming works ongoing at site |
Thiruvananthapuram Project AE7 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/12/2022 |
Scheduled date of Completion of the Project |
13 Aug 2022 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2017 |
TS Date |
21 Mar 2022 |