Project | Jal Jeevan Mission (JJM) - CWSS to Nattika Firka- Engandiyur Grama Panchayath- Shifting connections-Shifting house connections-Pipeline Work |
---|---|
Project Code | TCRJJM112111744P7 |
Type | Package |
Main Project | JJM-WSS TO NATTIKA FIRKA Phase II - Engandiyur Grama Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM) - CWSS to Nattika Firka- Engandiyur Grama Panchayath- Shifting connections-Shifting house connections-Pipeline Work |
Status | On-going |
District | Thrissur |
Executing Office | Vadanappalli Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 296000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/7324/2023_26_1_1 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 11/03/2024 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 11 Mar 2024 |
---|---|
Estimate Approval | 11 Mar 2024 |
Vadanappilly AE |
Date: 12/06/2024 |
Work in progress | 9% Completed
15 connections shifted.
Vadanappilly AE |
Date: 27/04/2024 |
Work in progress | 9% Completed
15 connections shifted.