JJM - Phase II- Kumily Panchayath: Providing Functional Household Tap Connection in 2021 - 24

Project JJM - Phase II- Kumily Panchayath: Providing Functional Household Tap Connection in 2021 - 24
Project Code IDKJJM022212231
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Supply and laying distribution network, construction of service reservoirs and providing FHTCs.
Status On-going
District Idukki
Executing Office Peerumedu Sn
AS Amount (Rs) 326700000
AS Number GO (RT) no134/2022/WRD
TS Amount (Rs) 316000000
TS Number WRD/KWA-CE(CR)/EST_TS/14955/2023_26_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 30000
Capacity in MLD 4.75
Actual Project Completion Date 09 Oct 2024
Coverage Kumily

Packages

No. Project Name Location View
1 JJM - Phase II- Kumily Panchayath: Providing Functional Household Tap Connection in 2021 - 24 Peerumedu Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 May 2024 1200 nos of FHTC provided Peerumedu Sn AE
11 Apr 2024 1000 nos of FHTC provided Peerumedu Sn AE
14 Mar 2024 592 nos of FHTC provided Peerumedu Sn AE
28 Feb 2024 501 nos of FHTC provided Peerumedu Sn AE
15 Feb 2024 402 nos of FHTC provided Peerumedu Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/10/2023
Scheduled date of Completion of the Project 19 Oct 2024
Expected date of Completion 19/10/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 29 Jul 2023