Project | Jal Jeevan Mission - Kannur District - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur Phase III .Construction of 2.5LL OHSR,Supplying and Laying of Pumping main Distribution System and providing FHTCs. |
---|---|
Project Code | KNRJJM092210431P1 |
Type | Package |
Main Project | Jal Jeevan Mission - Kannur District - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur Phase III . Construction of 2.50LL OHSR,Supplying and Laying of Pumping main and Distribution System and providing FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission - Kannur District - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur Phase III - Construction of 2.5LL OHSR,Supplying and Laying of Pumping main Distribution System and providing FHTCs. |
Status | On-going |
District | Kannur |
Executing Office | Irikkur HW Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 89101715 |
TS Number | TS/2021-2022/2022/3137 |
Technical specification | Jal Jeevan Mission - Kannur District - Padiyur-Kalliad Grama Panchayath-WSS to Padiyur-Vayathur Phase III - Construction of 2.5LL OHSR,Supplying and Laying of Pumping main Distribution System and providing FHTCs. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 05/05/2022 |
---|---|
Scheduled date of Completion as per agreement | 27 Jan 2023 |
Expected date of Completion | 10/05/2024 |
TS Date | 28 Jan 2022 |
---|---|
Estimate Approval | 18 Sep 2021 |
Workorder Date | 27 Apr 2022 |
---|
Thaliparamba WS Dn EE |
Date: 29/06/2024 |
Work has been completed | 100% Completed
Work completed and bill under preparation.
Thaliparamba WS Dn EE |
Date: 28/06/2024 |
Work has been completed | 100% Completed
Work completed and bill under preparation.