JJM - Minor line Extension and last mile connectivity by providing 65 mm GI pipe & 63 mm PVC pipe and providing FHTC at various wards in Perayam Panchayath.
Project |
JJM - Minor line Extension and last mile connectivity by providing 65 mm GI pipe & 63 mm PVC pipe and providing FHTC at various wards in Perayam Panchayath. |
Project Code |
KLMJJM082015585 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Minor line Extension and last mile connectivity by providing 65 mm GI pipe & 63 mm PVC pipe and providing FHTC at various wards in Perayam Panchayath. |
Status |
Completed |
District |
Kollam |
Executing Office |
Kundara PH Sn |
AS Amount (Rs) |
144230000
|
AS Number |
G.O.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
3929000 |
TS Number |
8408/2023-2024 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
25000 |
Capacity in MLD |
16.00 |
Actual Project Completion Date |
29 Feb 2024 |
Coverage |
Perayam Panchayath |
Packages
No. |
Project Name |
Location |
View |
No Packages has been added for this project. |
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
work completed |
Kundara PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/10/2023 |
Scheduled date of Completion of the Project |
26 Jan 2024 |
Expected date of Completion |
29/02/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
23 Jul 2023 |