- Home
- DEPOSIT-Shifting of KWA pipe lines for t...
DEPOSIT-Shifting of KWA pipe lines for the construction of ROB at Polayathode -Shifting of KWA pipe lines for the construction of ROB at Polayathode-Pipeline Work
| Project |
DEPOSIT-Shifting of KWA pipe lines for the construction of ROB at Polayathode -Shifting of KWA pipe lines for the construction of ROB at Polayathode-Pipeline Work |
| Project Code |
KLMDEPO082518359 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
DEPOSIT-Shifting of KWA pipe lines for the
construction of ROB at Polayathode -Shifting
of KWA pipe lines for the construction of ROB
at Polayathode-Pipeline Work
|
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Kollam WS Sn 3 |
| AS Amount (Rs) |
1402000
|
| AS Number |
KRDCL/532/2019/872 |
| TS Amount (Rs) |
1308000 |
| TS Number |
WRD/KWA-CE(SR)/EST_TS/10894/2022_26_1_1 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
2500 |
| Capacity in MLD |
1.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
2500 |
Packages
| No. |
Project Name |
Location |
View |
| No Packages has been added for this project. |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 01 Jul 2026 |
site hand over not done |
Kollam WS Sub Dn - AEE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
13/07/2025 |
| Scheduled date of Completion of the Project |
13 Oct 2025 |
| Expected date of Completion |
31/07/2026 |
Processing Dates
| AS Date |
13 Aug 2026 |
| TS Date |
20 Dec 2025 |