Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jan 2023 | WTP tank cleaning works. | Kattapana Project Dn AE4 | |
25 Jan 2023 | Leak rectification in 300 mm DI - K9 pipe from WTP to tank S1 | Kattapana Project Dn AE4 | |
23 Jan 2023 | WTP Sump cleaning and Trial run done | Kattapana Project Dn AE4 | |
11 Jan 2023 | Raw water pumping main Charged Successfully | Kattapana Project Dn AE4 | |
29 Dec 2022 | Line charging and leak Rectification work of Raw water pumping main in Progress. | Kattapana Project Dn AE4 | |
16 Dec 2022 | Electrical Charging completed at RWPH and WTP Ellackal Vellathooval on 16/12/2022 | Kattapana Project Dn AE4 | |
24 Feb 2022 | pipe laying work started | Kattappana Project Dn EE | |
03 Feb 2022 | GI Pipe of size 150 mm ,125 mm ,100 mm ,80 mm , 60 mm and 40 mm Supplied for the work. | Kattapana Project Dn AE4 | |
15 Nov 2021 | Providing FHTC not started because the scheme not yet commissioned | Kattapana Project Dn AE4 | |
07 Nov 2021 | Providing FHTC not started because the scheme not yet commissioned | Kattapana Project Dn AE4 |