Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jan 2023 WTP tank cleaning works. Kattapana Project Dn AE4
25 Jan 2023 Leak rectification in 300 mm DI - K9 pipe from WTP to tank S1 Kattapana Project Dn AE4
23 Jan 2023 WTP Sump cleaning and Trial run done Kattapana Project Dn AE4
11 Jan 2023 Raw water pumping main Charged Successfully Kattapana Project Dn AE4
29 Dec 2022 Line charging and leak Rectification work of Raw water pumping main in Progress. Kattapana Project Dn AE4
16 Dec 2022 Electrical Charging completed at RWPH and WTP Ellackal Vellathooval on 16/12/2022 Kattapana Project Dn AE4
24 Feb 2022 pipe laying work started Kattappana Project Dn EE
03 Feb 2022 GI Pipe of size 150 mm ,125 mm ,100 mm ,80 mm , 60 mm and 40 mm Supplied for the work. Kattapana Project Dn AE4
15 Nov 2021 Providing FHTC not started because the scheme not yet commissioned Kattapana Project Dn AE4
07 Nov 2021 Providing FHTC not started because the scheme not yet commissioned Kattapana Project Dn AE4