Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Oct 2023 | Leak maintenance & Connection works in progress | Kattapana Project Dn AE4 | |
06 Oct 2023 | Leak maintenance & Connection works in progress | Kattapana Project Dn AE4 | |
03 Oct 2023 | Connection works in progress | Kattapana Project Dn AE4 | |
28 Sep 2023 | Connection works in progress | Kattapana Project Dn AE4 | |
25 Sep 2023 | Connection works in progress | Kattapana Project Dn AE4 | |
21 Sep 2023 | Connection works in progress | Kattapana Project Dn AE4 | |
18 Sep 2023 | Connection works in progress | Kattapana Project Dn AE4 | |
14 Sep 2023 | Leak Rectification and Connection works in progress | Kattapana Project Dn AE4 | |
11 Sep 2023 | Connection works in progress | Kattapana Project Dn AE4 | |
07 Sep 2023 | Connection works in progress | Kattapana Project Dn AE4 |