| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Dec 2022 | extension of distribution line with 63 mm PVC CL3 pipe at various places of ward no.12 in Kunnathoor Grama Panchayath - work 100 % completed | Sasthamcotta WS Sn 1 - AE | |
| 06 Dec 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 750 m work completed. Balance work is on progress | Sasthamcotta WS Sn 1 - AE | |
| 30 Nov 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress | Sasthamcotta WS Sn 1 - AE | |
| 28 Nov 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress | Sasthamcotta WS Sn 1 - AE | |
| 26 Nov 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress | Sasthamcotta WS Sn 1 - AE | |
| 24 Nov 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed. Balance work is on progress | Sasthamcotta WS Sn 1 - AE | |
| 21 Nov 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 670 m work completed | Sasthamcotta WS Sn 1 - AE | |
| 16 Nov 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 650 m work completed | Sasthamcotta WS Sn 1 - AE | |
| 14 Nov 2022 | 63 mm PVC pipe line laying work in various wards - work on progress. Out of 750 m laying work 550 m work completed. | Sasthamcotta WS Sn 1 - AE | |
| 09 Nov 2022 | 63 mm PVC Pipeline extension work started. 60 m pipe line laying work completed. | Sasthamcotta WS Sn 1 - AE |