| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Sep 2022 | Work completed | Kollam QC AE | |
| 17 Jun 2022 | Physical-chemical area completed | Kollam QC AE | |
| 16 Apr 2022 | Truss work in progress plastering finished | Kollam QC AE | |
| 07 Apr 2022 | Slab work finished up to roof level completed. Truss work on progress | Kollam QC AE | |
| 18 Mar 2022 | Brickwork ongoing lintel level completed. Window and slab work ongoing | Kollam QC AE | |
| 04 Mar 2022 | Brick work and slab work ongoing | Kollam QC AE | |
| 25 Feb 2022 | Floor work finished , brick work started | Kollam QC AE | |
| 28 Jan 2022 | Earth filling completed, floor concreting work will start soon after soil setting | Kollam QC AE | |
| 18 Jan 2022 | Site clearance and earth filling on progress | Kollam QC AE | |
| 10 Jan 2022 | The entrance of the lab is shifted to the opposite direction due to the high expansion expected and site clearing in progress | Kollam QC AE |