01 Sep 2022 Work completed Kollam QC AE
17 Jun 2022 Physical-chemical area completed Kollam QC AE
16 Apr 2022 Truss work in progress plastering finished Kollam QC AE
07 Apr 2022 Slab work finished up to roof level completed. Truss work on progress Kollam QC AE
18 Mar 2022 Brickwork ongoing lintel level completed. Window and slab work ongoing Kollam QC AE
04 Mar 2022 Brick work and slab work ongoing Kollam QC AE
25 Feb 2022 Floor work finished , brick work started Kollam QC AE
28 Jan 2022 Earth filling completed, floor concreting work will start soon after soil setting Kollam QC AE
18 Jan 2022 Site clearance and earth filling on progress Kollam QC AE
10 Jan 2022 The entrance of the lab is shifted to the opposite direction due to the high expansion expected and site clearing in progress Kollam QC AE