| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Apr 2026 | Revised estimate and Part bill submitted. | Keezhallur PH Sn AE | |
| 26 Mar 2026 | Revised estimate and Part bill submitted | Keezhallur PH Sn AE | |
| 16 Mar 2026 | PIPE LAYING WORK COMPLETED. | Keezhallur PH Sn AE | |
| 06 Mar 2026 | Pipe line laying work completed, Revised Estimate under Preparation | Keezhallur PH Sn AE | |
| 27 Feb 2026 | PIPE LINE LAYING WORK COMPLETED | Keezhallur PH Sn AE | |
| 18 Feb 2026 | PIPE LAYING WORK COMPLETED. | Keezhallur PH Sn AE | |
| 09 Feb 2026 | Pipe line laying completed | Keezhallur PH Sn AE | |
| 28 Jan 2026 | Pipe line laying completed | Keezhallur PH Sn AE | |
| 19 Jan 2026 | ROAD CROSSSING WORK COMPLETED | Keezhallur PH Sn AE | |
| 12 Jan 2026 | GI FABRICATING WORK PROGRESSING | Keezhallur PH Sn AE |