| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Jul 2026 | COP Submitted | Keezhallur PH Sn AE | |
| 06 Jul 2026 | Demand notice issued - COP submitted | Keezhallur PH Sn AE | |
| 26 Jun 2026 | Road restoration work pending | Keezhallur PH Sn AE | |
| 17 Jun 2026 | Road restoration work pending | Keezhallur PH Sn AE | |
| 02 Jun 2026 | Pipe line laying work completed, Part bill submitted, road restoration work pending. | Keezhallur PH Sn AE | |
| 22 May 2026 | Pipe line laying work completed, Part bill submitted. | Keezhallur PH Sn AE | |
| 12 May 2026 | Pipe line laying work completed, Part bill submitted. | Keezhallur PH Sn AE | |
| 02 May 2026 | Part bill submitted | Keezhallur PH Sn AE | |
| 25 Apr 2026 | Part bill submitted | Keezhallur PH Sn AE | |