07 Jun 2024 | Work tendered twice with due date 30.03.2022 and 09.08.2022 but no offer received | Thodupuzha PH Sn | |
05 Jun 2024 | Work tendered twice with due date 30.03.2022 and 09.08.2022 but no offer received | Thodupuzha PH Sn | |
03 Jun 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn | |
29 May 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn | |
24 May 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn | |
23 May 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn | |
20 May 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn | |
17 May 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn | |
15 May 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn | |
13 May 2024 | 257 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M | Thodupuzha PH Sn |