05 Jan 2024 192 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
03 Jan 2024 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
01 Jan 2024 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
29 Dec 2023 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
26 Dec 2023 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
22 Dec 2023 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
15 Dec 2023 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
13 Dec 2023 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
11 Dec 2023 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn
08 Dec 2023 180 FHTC Given ,Newly laid line-50 mm GI-737.20 m, 65mm GI-484.60 m.50 mm GI -737.20 M ,65 mm GI -484.60 M Thodupuzha PH Sn