| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Sep 2026 | Road cutting demand note issued.COP Submitted to higher office. | Kannur WS Sn AE 2 | |
| 14 Aug 2026 | Work order issued. pipe supplied. Site handed over. Road cutting permission pending | Kannur WS Sn AE 2 | |
| 17 Jul 2026 | Work order issued. pipe supplied. Site handed over. | Kannur WS Sn AE 2 | |
| 07 Jul 2026 | Work order issued. Site handed over. | Kannur WS Sn AE 2 | |
| 18 Jun 2026 | Work order issued. Site handed over. | Kannur WS Sn AE 2 | |
| 04 Jun 2026 | Work order issued. Site handed over. | Kannur WS Sn AE 2 | |
| 29 Apr 2026 | Work order issued. | Kannur WS Sn AE 2 | |
| 17 Apr 2026 | Work order issued. | Kannur WS Sn AE 2 | |
| 08 Apr 2026 | Work order issued. | Kannur WS Sn AE 2 | |
| 24 Mar 2026 | Work order issued. | Kannur WS Sn AE 2 |