Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Dec 2022 | 4465 nos JJM connections given in this project out of which 4413 nos billed | Aluva AE JJM | |
09 Dec 2022 | 4465 nos JJM connections given in this project out of which 4413 nos billed | Aluva AE JJM | |
07 Dec 2022 | 4437 nos JJM connections given in this project out of which 4413 nos billed | Aluva AE JJM | |
05 Dec 2022 | 4413 nos JJM connections given in this project out of which 4413 nos billed | Aluva AE JJM | |
03 Dec 2022 | 4413 nos JJM connections given in this project out of which 4413 nos billed | Aluva AE JJM | |
01 Dec 2022 | 4413 nos JJM connections given in this project out of which 4413 nos billed | Aluva AE JJM | |
28 Nov 2022 | 4404 nos JJM connections given in this project out of which 4162 nos billed | Aluva AE JJM | |
26 Nov 2022 | 4404 nos JJM connections given in this project out of which 4162 nos billed | Aluva AE JJM | |
24 Nov 2022 | 4313 nos JJM connections given in this project out of which 4162 nos billed | Aluva AE JJM | |
21 Nov 2022 | 4285 nos JJM connections given in this project out of which 4162 nos billed | Aluva AE JJM |