15 Jun 2021 The various components - Intake structure ,Treatment plant, RWPM ,CWPM's and Pump sets ,Service Reservoirs ,Distribution networks for Zones 1,2,3,4,5,8,9, etc are completed under ARP-NRDWP. The balance works such as RW Pump set, Transformer at RW Pump house ,Power Connection works ,Charging of Pumping mains and Dist. networks & FHTC's etc are ongoing under state plan and JJM . Kattappana Project Dn EE
05 May 2021 The various components - Intake structure ,Treatment plant, RWPM ,CWPM's and Pump sets ,Service Reservoirs ,Distribution networks for Zones 1,2,3,4,5,8,9, etc are completed under ARP-NRDWP. The balance works such as RW Pump set, Transformer at RW Pump house ,Power Connection works ,Charging of Pumping mains and Dist. networks & FHTC's etc are ongoing under state plan and JJM . Kattappana Project Dn EE
04 May 2021 Raw water pumpsets 3 nos (100 HP) supplied by the contractor under state plan Kattapana Project Dn AE4
26 Apr 2021 The supply of Raw water pumpsets arranged under state plan. The charging of distribution arranged under JJM. Kattappana Project Dn EE
21 Mar 2021 The testing of Raw water pumpsets is progressing Kattapana Project Dn AE4
08 Feb 2021 The Raw water pumpsets will be suppled soon as informed by the contractor Kattapana Project Dn AE4
03 Feb 2021 The contractor informed that the Raw water pump set will be supplied soon Kattappana Project Dn EE
27 Jan 2021 Contractor agreed to supply the Raw water pump sets soon. Kattappana Project Dn EE
17 Nov 2020 Raw water pumpset work arranged UNDER STATE PLAN . Kattapana Project Dn AE4
11 Nov 2020 C/W PUMPS ERECTION COMPLETED, R/W PUMPS WORK ARRANGED UNDER STATE PLAN . COMMISSIONING WORKS ARRANGED IN JJM Kattappana Project Dn EE