Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2023 Providing urgent FHTC are in progress , pipes order placed, tank site earth work on going. Survey work on going at WTP site. Piravam Project Sub Dn AE 2
07 Sep 2023 providing urgent FHTC are in progress. Piravam Project Sub Dn AE 2
24 Aug 2023 providing urgent FHTC are in progress Piravam Project Sub Dn AE 2
17 Aug 2023 providing urgent FHTC are in progress Piravam Project Sub Dn AE 2
11 Aug 2023 providing urgent FHTC are in progress Piravam Project Sub Dn AE 2
29 Jul 2023 Site cleared for tanks.Supply order of pipes placed. Piravam Project Sub Dn AE 2
19 Jul 2023 Tank sites cleared.Supply order of pipes(part) placed by contractor Piravam Project Sub Dn AE 2
04 Jul 2023 Agreement executed Piravam Project Sub Dn AE 2
30 Jun 2023 WORK ORDER ISSUED ON 24/03/2023 Piravam Project Sub Dn AE 2
27 Jun 2023 WORK ORDER ISSUED ON 24/03/2023 Piravam Project Sub Dn AE 2