Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2023 | Providing urgent FHTC are in progress , pipes order placed, tank site earth work on going. Survey work on going at WTP site. | Piravam Project Sub Dn AE 2 | |
07 Sep 2023 | providing urgent FHTC are in progress. | Piravam Project Sub Dn AE 2 | |
24 Aug 2023 | providing urgent FHTC are in progress | Piravam Project Sub Dn AE 2 | |
17 Aug 2023 | providing urgent FHTC are in progress | Piravam Project Sub Dn AE 2 | |
11 Aug 2023 | providing urgent FHTC are in progress | Piravam Project Sub Dn AE 2 | |
29 Jul 2023 | Site cleared for tanks.Supply order of pipes placed. | Piravam Project Sub Dn AE 2 | |
19 Jul 2023 | Tank sites cleared.Supply order of pipes(part) placed by contractor | Piravam Project Sub Dn AE 2 | |
04 Jul 2023 | Agreement executed | Piravam Project Sub Dn AE 2 | |
30 Jun 2023 | WORK ORDER ISSUED ON 24/03/2023 | Piravam Project Sub Dn AE 2 | |
27 Jun 2023 | WORK ORDER ISSUED ON 24/03/2023 | Piravam Project Sub Dn AE 2 |