| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Dec 2025 | Pipe laying work in progress, 4030.1 m pipe laid. | Kollam WS Sn 3 - AE | |
| 01 Dec 2025 | Pipe laying work in progress, 4030.1 m pipe laid. | Kollam WS Sn 3 - AE | |
| 25 Nov 2025 | Pipe laying work in progress, 4030.1 m pipe laid. | Kollam WS Sn 3 - AE | |
| 21 Nov 2025 | Pipe laying work in progress, 4030.1 m pipe laid | Kollam WS Sn 3 - AE | |
| 17 Nov 2025 | Pipe laying work in progress, 4030.1 m pipe laid | Kollam WS Sn 3 - AE | |
| 15 Nov 2025 | Pipe laying work in progress, 4030.1 m pipe laid | Kollam WS Sn 3 - AE | |
| 10 Nov 2025 | Pipe laying work in progress, 4030.1 m pipe laid | Kollam WS Sn 3 - AE | |
| 05 Nov 2025 | Pipe laying work in progress, 4030.1 m pipe laid | Kollam WS Sn 3 - AE | |
| 30 Oct 2025 | Pipe laying work in progress, 3917.9 m pipe laid | Kollam WS Sn 3 - AE | |
| 25 Oct 2025 | Pipe laying work in progress 3874.7 m pipe laying completed | Kollam WS Sn 3 - AE |