| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 May 2025 | Pipe laying work in progress 3830 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 02 May 2025 | Pipe laying work in progress 3830 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 28 Apr 2025 | Pipe laying work in progress 3830 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 24 Apr 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 21 Apr 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 19 Apr 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 11 Apr 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 07 Apr 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 02 Apr 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 29 Mar 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE |