Status Date Overall Project Status Project Officer Contact
25 Mar 2025 Pipe laying work in progress 2750.3 m pipe laying completed Kollam WS Sn 3 - AE
20 Mar 2025 Pipe laying work in progress 2750.3 m pipe laying completed Kollam WS Sn 3 - AE
17 Mar 2025 Pipe laying work in progress 2750.3 m pipe laying completed. Kollam WS Sn 3 - AE
14 Mar 2025 Pipe laying work in progress 2750.3 m pipe laying completed. Kollam WS Sn 3 - AE
11 Mar 2025 Pipe laying work in progress 2750.3 m pipe laying completed. Kollam WS Sn 3 - AE
07 Mar 2025 Pipe laying work in progress 2750.3 m pipe laying completed. Kollam WS Sn 3 - AE
05 Mar 2025 Pipe laying work in progress 2508 m pipe laying completed. Kollam WS Sn 3 - AE
01 Mar 2025 Pipe laying work in progress 2508 m pipe laying completed. Kollam WS Sn 3 - AE
24 Feb 2025 Pipe laying work in progress 2508 m pipe laying completed. Kollam WS Sn 3 - AE
19 Feb 2025 Pipe laying work in progress 2508 m pipe laying completed. Kollam WS Sn 3 - AE