| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Mar 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 20 Mar 2025 | Pipe laying work in progress 2750.3 m pipe laying completed | Kollam WS Sn 3 - AE | |
| 17 Mar 2025 | Pipe laying work in progress 2750.3 m pipe laying completed. | Kollam WS Sn 3 - AE | |
| 14 Mar 2025 | Pipe laying work in progress 2750.3 m pipe laying completed. | Kollam WS Sn 3 - AE | |
| 11 Mar 2025 | Pipe laying work in progress 2750.3 m pipe laying completed. | Kollam WS Sn 3 - AE | |
| 07 Mar 2025 | Pipe laying work in progress 2750.3 m pipe laying completed. | Kollam WS Sn 3 - AE | |
| 05 Mar 2025 | Pipe laying work in progress 2508 m pipe laying completed. | Kollam WS Sn 3 - AE | |
| 01 Mar 2025 | Pipe laying work in progress 2508 m pipe laying completed. | Kollam WS Sn 3 - AE | |
| 24 Feb 2025 | Pipe laying work in progress 2508 m pipe laying completed. | Kollam WS Sn 3 - AE | |
| 19 Feb 2025 | Pipe laying work in progress 2508 m pipe laying completed. | Kollam WS Sn 3 - AE |