| 20 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE | |
| 19 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE | |
| 18 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE | |
| 17 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE | |
| 16 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE | |
| 15 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE | |
| 15 Feb 2021 | 873 Nos FHTC provided , | Kaduthuruthy Dn EE | |
| 14 Feb 2021 | 849 Nos FHTC provided , IMIS entry-552Nos (ID -2020/14144, As No.GO (Rt) No.541/2020/WRD, TS No.TS/2020-2021/2020/14144 Dated: 27-08-2020(Amount -54080000),Contractor - R. Santhoshkumar, Agt.No.17/SE/PHCK/20-21Dt.16.10.20, Sanctioned FHTC - 2100Nos) | Kaduthuruthy Dn EE | |
| 14 Feb 2021 | 849 FHTC provided .fhtc work in ward 6 &12 is progressing | Kaduthuruthy Dn EE | |
| 12 Feb 2021 | 788 FHTC PROVIDED. NEW FHTC WORKS – WARD NO: 6,12,13, IN PROGRESS TODAY. | Kaduthuruthy Dn EE |