| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Mar 2021 | Pipe laying work in progress | Kaduthuruthy Dn EE | |
| 03 Mar 2021 | No work at the site .due to contractors strike.geo tagging in progressing | Kaduthuruthy Dn EE | |
| 02 Mar 2021 | No work at site due to contractors strike Geo Tagging in Progress | Kaduthuruthy Dn EE | |
| 01 Mar 2021 | 3rd Party inspection completed for 583 FHTC | Kaduthuruthy Dn EE | |
| 27 Feb 2021 | Geo Tagging in Progress | Kaduthuruthy Dn EE | |
| 26 Feb 2021 | Geo Tagging in Progress | Kaduthuruthy Dn EE | |
| 25 Feb 2021 | Geo Tagging in Progress | Kaduthuruthy Dn EE | |
| 24 Feb 2021 | Geo Tagging in Progress | Kaduthuruthy Dn EE | |
| 23 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE | |
| 22 Feb 2021 | 873 FHTC provided.geo tagging in progress | Kaduthuruthy Dn EE |