| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Feb 2022 | No work | Kaduthuruthy Dn EE | |
| 14 Feb 2022 | Work at ward 1 | Kaduthuruthy Dn EE | |
| 13 Feb 2022 | No work | Kaduthuruthy Dn EE | |
| 11 Feb 2022 | No work | Kaduthuruthy Dn EE | |
| 10 Feb 2022 | No work | Kaduthuruthy Dn EE | |
| 10 Feb 2022 | No work | Kaduthuruthy Dn EE | |
| 09 Feb 2022 | No work Due to Delay in getting sanction for laying pipe line in Kallara-Vechoor road from Udayamthara to Perumthuruth(1750m) | Kaduthuruthy Dn EE | |
| 08 Feb 2022 | No work | Kaduthuruthy Dn EE | |
| 07 Feb 2022 | No work | Kaduthuruthy Dn EE | |
| 05 Feb 2022 | Work at ward 3,7,8. | Kaduthuruthy Dn EE |