| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Dec 2021 | providing FHTC in ward 2,3,8 | Kaduthuruthy Dn EE | |
| 17 Dec 2021 | no work | Kaduthuruthy Dn EE | |
| 16 Dec 2021 | Total FHTC provided 1464 out of 2100. Total pipe line laid -13840m (160mm PVC-2800m,110mm PVC 700m,90mm PVC -10000m 80mm GI-340m). Balance pipe line to be laid (80m GI - 3160m). Total FHTC billed -1462. Total billed Amount-21879713.75/- .Work delayed due to pending road cutting sanction from PWD. For laying 160mm PVC pipe line -1.75Km on PWD road, applied through Row portal on 12/11/2020(Row/101089,Row/101090)and the application are reverted with reason ''returned as per road condition Row application again resubmitted on 18/02/2021 (Row/1015641,Row/1015640) again application was reverted with reason'' application considering after Monsoon . So the work was temporarily stopped due to non getting of PWD sanction. | Kaduthuruthy Dn EE | |
| 15 Dec 2021 | no work | Kaduthuruthy Dn EE | |
| 14 Dec 2021 | no work | Kaduthuruthy Dn EE | |
| 13 Dec 2021 | no work | Kaduthuruthy Dn EE | |
| 10 Dec 2021 | providing FHTC in ward 1,2 | Kaduthuruthy Dn EE | |
| 09 Dec 2021 | providing FHTC in ward 1 | Kaduthuruthy Dn EE | |
| 08 Dec 2021 | no work | Kaduthuruthy Dn EE | |
| 07 Dec 2021 | no work | Kaduthuruthy Dn EE |