| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Feb 2023 | Work completed and final bill submitted | Oachira AE | |
| 04 Feb 2023 | work completed bill under preparation | Oachira AE | |
| 01 Feb 2023 | work completed bill under preparation | Oachira AE | |
| 30 Jan 2023 | work completed bill under preparation | Chavara AEE | |
| 27 Jan 2023 | Work completed | Oachira AE | |
| 26 Jan 2023 | Work in progress | Oachira AE | |
| 25 Jan 2023 | Work in progress | Oachira AE | |
| 23 Jan 2023 | Work in progress | Oachira AE | |
| 20 Jan 2023 | Work in progress | Oachira AE | |
| 18 Jan 2023 | Work in progress | Oachira AE |