Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Feb 2022 | no work | Kaduthuruthy Dn EE | |
16 Feb 2022 | no work | Kaduthuruthy Dn EE | |
15 Feb 2022 | no work | Kaduthuruthy Dn EE | |
14 Feb 2022 | no work | Kaduthuruthy Dn EE | |
11 Feb 2022 | Today work at ward 6 connection work | Kaduthuruthy Dn EE | |
10 Feb 2022 | today work at ward 15 | Kaduthuruthy Dn EE | |
09 Feb 2022 | Pipe laying work at ambanappalli road 63 mm pvc laid 118.20 mtr Delay in sanctioning RE,and providing additional pipe line to give FHTC . Delay in getiing PWD sanction | Kaduthuruthy Dn EE | |
08 Feb 2022 | total FHTC GIVEN 1021 Today work jjm pipe laying ward 15 | Kaduthuruthy Dn EE | |
07 Feb 2022 | total FHTC GIVEN 1021 Today work jjm pipe laying ward 15 | Kaduthuruthy Dn EE | |
07 Feb 2022 | no work | Kaduthuruthy Dn EE |