| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Sep 2023 | work completed | Thaliparamba WS Dn EE | |
| 13 Sep 2023 | pumping main 350mm - 1574.5 m pumping main 250mm -1942 m pumping main 90mm PE -2270 m Transmission main 350 mm - 875 m Transmission main 350 mm - 482 m | Thaliparamba WS Dn EE | |
| 11 Sep 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE | |
| 07 Sep 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE | |
| 04 Sep 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE | |
| 01 Sep 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE | |
| 25 Aug 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE | |
| 21 Aug 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE | |
| 18 Aug 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE | |
| 16 Aug 2023 | PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING | Thaliparamba WS Dn EE |