Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Oct 2022 | Except Package 1 & 5 , 100% of all other works completed. | Kanhangad Proj Dn AEE - 1 | |
25 Aug 2022 | Except Package 1 & 5 , 100% of all other works completed. | Kanhangad Proj Dn AEE - 1 | |
16 Aug 2022 | Except Package 1 & 5 , 100% of all other works completed. | Kanhangad Proj Dn AEE - 1 | |
16 Aug 2022 | work completed and commissioned ,FCC submitted. | Kanhangad Proj Dn AEE - 1 | |
07 Mar 2022 | Except package 5, 100 % of all other works completed | Kanhangad Proj Dn AEE - 1 | |
25 Feb 2021 | Except package 5, 97% of all other works completed | Kannur Project Dn EE | |
11 Feb 2021 | For laying dedicated UG cable from Vidyanagar to Bavikkara an amount of Rs 38154526/- deposited to KSEB | Kanhangad Proj Dn AEE - 1 | |
02 Feb 2021 | Ovrall 69% completed | Kanhangad Proj Dn AEE - 1 | |
29 Jan 2021 | Overall 69% completed | Kanhangad Proj Dn AEE - 1 | |
16 Nov 2020 | Overall 67% completed. | Kanhangad Proj Dn AEE - 1 |