| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Jan 2023 | Work order issued, agreement not executed | Sasthamcotta WS Sn 1 - AE | |
| 19 Jan 2023 | Work order issued, agreement not executed | Sasthamcotta WS Sn 1 - AE | |
| 16 Jan 2023 | Work order issued, agreement not executed | Sasthamcotta WS Sn 1 - AE | |
| 09 Jan 2023 | Work order issued. | Sasthamcotta WS Sn 1 - AE | |
| 05 Jan 2023 | Work order issued | Sasthamcotta WS Sub-Dn - AEE | |
| 03 Jan 2023 | Work tendered. | Sasthamcotta WS Sn 1 - AE | |
| 29 Dec 2022 | Work tendered | Sasthamcotta WS Sn 1 - AE | |
| 14 Dec 2022 | Work tendered. | Sasthamcotta WS Sub-Dn - AEE |