25 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn
24 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn
23 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn
22 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn
19 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn
18 Mar 2022 Package 1 - 64% and package 2 - 80% completed Cherthala PH SUb Dn
17 Mar 2022 Package 1 - 64% and package 2 - 80% completed Cherthala PH SUb Dn
16 Mar 2022 Package 1 - 64% and package 2 - 80% completed Cherthala PH SUb Dn
14 Mar 2022 Package 1 - 62 % and package 2 - 80% completed Cherthala PH SUb Dn
11 Mar 2022 Package 1 - 62 % and package 2 - 80% completed Cherthala PH SUb Dn