08 Apr 2022 Package 1 - 64% and package 2 - completed Cherthala PH SUb Dn
07 Apr 2022 Package 1 - 64% and package 2 - completed Cherthala PH SUb Dn
06 Apr 2022 Package 1 - 64% and package 2 - completed Cherthala PH SUb Dn
05 Apr 2022 Package 1 - 64% and package 2 - completed Cherthala PH SUb Dn
04 Apr 2022 Package 1 - 64% and package 2 - completed Cherthala PH SUb Dn
02 Apr 2022 Package 1 - 64% and package 2 - completed Cherthala PH SUb Dn
01 Apr 2022 Package 1 - 64% and package 2 - completed Cherthala PH SUb Dn
31 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn
30 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn
26 Mar 2022 Package 1 - 64% and package 2 - 95% completed Cherthala PH SUb Dn