Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Nov 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
11 Nov 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
10 Nov 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
06 Nov 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
05 Nov 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
03 Nov 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
02 Nov 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
29 Oct 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
27 Oct 2021 FHTCs given 1035/1840. Cherthala PH SUb Dn
26 Oct 2021 FHTCs given 1035/1840. For satisfactory completion of the work, additional pipe line extension required. Hence proposal for the same submitted to Division office for approval. Cherthala PH SUb Dn