Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Dec 2021 | FHTCs given 1093/1840 | Cherthala PH SUb Dn | |
23 Dec 2021 | FHTCs given 1073/1840 | Cherthala PH SUb Dn | |
22 Dec 2021 | FHTCs given 1055/1840 | Cherthala PH SUb Dn | |
21 Dec 2021 | FHTCs given 1050/1840 | Cherthala PH SUb Dn | |
20 Dec 2021 | FHTCs given 1050/1840 | Cherthala PH SUb Dn | |
18 Dec 2021 | FHTCs given 1045/1840 | Cherthala PH SUb Dn | |
17 Dec 2021 | FHTCs given 1040/1840 | Cherthala PH SUb Dn | |
16 Dec 2021 | FHTCs given 1040/1840 | Cherthala PH SUb Dn | |
15 Dec 2021 | FHTCs given 1040/1840 | Cherthala PH SUb Dn | |
14 Dec 2021 | FHTCs given 1040/1840 | Cherthala PH SUb Dn |