Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Mar 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
22 Mar 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
20 Mar 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
18 Mar 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
15 Mar 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
13 Mar 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
11 Mar 2024 | Package I and II were shifted to JJM. Package III- Permission pending from Dam safety for weir construction. | Kattappana AEE 1 | |
07 Mar 2024 | Package I and II were shifted to JJM. Package III- Permission pending from Dam safety for weir construction. | Kattappana AEE 1 | |
05 Mar 2024 | Package I and II were shifted to JJM. Package III- Permission pending from Dam safety for weir construction. | Kattappana AEE 1 | |
02 Mar 2024 | Package I and II were shifted to JJM. Package III- Permission pending from Dam safety for weir construction. | Kattappana AEE 1 |