Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Sep 2022 Work completed Kollam QC AE
17 Jun 2022 All work bacteriology and physical chemical area completed Kollam QC AE
16 Apr 2022 Work Completed Kollam QC AE
07 Apr 2022 Work completed almost just some minor finishing left Kollam QC AE
18 Mar 2022 Titration table furniture fitting and final finishing in progress Kollam QC AE
04 Mar 2022 Partition work completed , door and finishing work in progress Kollam QC AE
25 Feb 2022 Partition and painting work in progress Kollam QC AE
28 Jan 2022 Granite work completed. Electrical wiring completed. False ceiling LED light fitting works in progress. Plumbing work in progress Kollam QC AE
21 Jan 2022 Granite work started, electrical, false ceiling works are ongoing. Slab work completed. Kollam QC AE
10 Jan 2022 Electrical work , false ceiling and slab work started Kollam QC AE