Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Feb 2022 | 9 nos FHTC completed | Kanjiramkulam AE JJM | |
24 Feb 2022 | 5 nos FHTC given, | Kanjiramkulam AE JJM | |
21 Feb 2022 | Replacement of AC pipe work started | Kanjiramkulam AE JJM | |
18 Feb 2022 | Work in progress | 1% Completed | | Neyyattinkara WS Dn EE | |
14 Feb 2022 | work started 2 nos FHTC given | Kanjiramkulam AE JJM | |
09 Feb 2022 | replacement of AC pipe -160mm pvc pipe supplied | Kanjiramkulam AE JJM | |
05 Feb 2022 | pipe not yet received | Kanjiramkulam AE JJM | |
03 Feb 2022 | demand notice received from PWD , recorded and submitted to Division office | Kanjiramkulam AE JJM | |
31 Jan 2022 | pipe not yet received | Kanjiramkulam AE JJM | |
27 Jan 2022 | supply of pipe order placed by the contractor , | Kanjiramkulam AE JJM |