Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 May 2022 cc 2nd and part bill submitted Kanjiramkulam AE JJM
28 Apr 2022 210 nos FHTC completed , waiting for 20 mm HDPE pipe additional length Kanjiramkulam AE JJM
25 Apr 2022 190 nos FHTC given Kanjiramkulam AE JJM
22 Apr 2022 164 nos FHTC given Kanjiramkulam AE JJM
18 Apr 2022 replacement of AC pipe work completed and 140 no fhtc given Kanjiramkulam AE JJM
16 Apr 2022 130 nos fhtc given Kanjiramkulam AE JJM
11 Apr 2022 110 nos FHTC given Kanjiramkulam AE JJM
07 Apr 2022 90 nos FHTC given Kanjiramkulam AE JJM
04 Apr 2022 72 nos FHTC given Kanjiramkulam AE JJM
30 Mar 2022 60 nos fhtc given- CC 1ST and part bill for 50 nos submitted Kanjiramkulam AE JJM