Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Feb 2024 | Pipe laying work ongoing | Ranni PH Sn - AE | |
03 Jan 2024 | Pipe Supply order given, pipe not received yet | Ranni PH Sn - AE | |
01 Jan 2024 | Pipe Supply order given, pipe not received yet | Ranni PH Sn - AE | |
30 Dec 2023 | Pipe Supply order given, pipe not received yet | Ranni PH Sn - AE | |
29 Dec 2023 | Pipe Supply order given, pipe not received yet | Ranni PH Sn - AE | |
28 Dec 2023 | Pipe Supply order given, pipe not received yet | Ranni PH Sn - AE | |
26 Dec 2023 | Pipe Supply order given, pipe not received yet | Ranni PH Sn - AE | |
22 Dec 2023 | Pipe Supply order given, pipe not received yet | Ranni PH Sn - AE | |
01 Dec 2023 | Pipe Supply order given, pipe not received yet | Pathanamthitta PH Dn EE | |
01 Dec 2023 | Ongoing | Pathanamthitta PH Dn EE |