Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
26 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
26 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
24 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
23 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
22 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
21 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
20 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
19 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|
18 Nov 2021 |
10902m 90mm PVC, 5440m 110mm PVC, 120m 100 mm GI and 340m 80mm GI pipes laid, 63 mm PVC laying work in progress, Total 1673 FHTCs provided |
Kaduthuruthy Dn EE |
|