01 Jun 2024 2.6 KM pipe laid 50 nos FHTC given Kannur PH Sn 3 AE
18 May 2024 2 KM pipe laid 32 nos FHTC given Kannur PH Sn 3 AE
02 May 2024 150 M pipe laid 32 nos FHTC given Kannur PH Sn 3 AE
24 Apr 2024 10 % COMPLETED. Kannur PH Sn 3 AE