Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jun 2024 | Work at ulloorkonam and manvila | Kazhakootam WW Sn AE | |
27 Jun 2024 | excavation and pipe laying work at Green field stadium and Manvila | Kazhakootam WW Sn AE | |
26 Jun 2024 | no work due to heavy rain | Kazhakootam WW Sn AE | |
25 Jun 2024 | excavation and pipe laying work at green field stadium , manvila , cheruvakkal | Kazhakootam WW Sn AE | |
24 Jun 2024 | excavation and pipe laying work at green field stadium, mankuzhi,manvila | Kazhakootam WW Sn AE | |
22 Jun 2024 | Pipe laying and excavation work at back side of greenfield stadium | Kazhakootam WW Sn AE | |
21 Jun 2024 | No work due to heavy rain | Kazhakootam WW Sn AE | |
20 Jun 2024 | no work due to heavy rain | Kazhakootam WW Sn AE | |
19 Jun 2024 | pipe laying , excavation work at alathara,kattela | Kazhakootam WW Sn AE | |
18 Jun 2024 | pipe laying and excavation work at chenkottukonam and alathara | Kazhakootam WW Sn AE |