Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 May 2022 | 350 mm DI pipe & 90 mm PVC pipe 165 m laid | Mattannur WS Sn | |
18 Apr 2022 | 30 % Pipe Supplied | Mattannur WS Sn | |
18 Apr 2022 | Pipe Supplied | Mattannur WS Sn | |
10 Apr 2022 | The contractor placed order for pipe supply and letter has been given to CIPET for pipe supply | Mattannur WS Sn | |
16 Mar 2022 | The contractor placed order for pipe supply and letter has been given to CIPET for pipe supply | Kannur PH Dn EE | |
16 Mar 2022 | Work order Issued to Contractor Sri. N Reghu and Agreement Executed | Kannur PH Dn EE | |
11 Mar 2022 | Work order issued | Mattannur WS Sn | |
21 Feb 2022 | Tender process stage | Mattannur WS Sn | |
16 Feb 2022 | Tender process stage | Mattannur WS Sn | |
09 Feb 2022 | Tender process stage | Mattannur WS Sn |