KIIFB-Project-7-Kolecherry WSS-Zone I-Replacing old 400/350 mm premo/AC pipe from Kothery GLtank to Vayanthode Jn. with 400 mm DI pipe

Project KIIFB-Project-7-Kolecherry WSS-Zone I-Replacing old 400/350 mm premo/AC pipe from Kothery GLtank to Vayanthode Jn. with 400 mm DI pipe
Project Code KNRKIIFB01192310
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Project-7-Kolecherry WSS-Zone I-Replacing old 400/350 mm premo/AC pipe from Kothery GLtank to Vayanthode Jn. with 400 mm DI pipe
Status Completed
District Kannur
Executing Office Kannur WS Dn
AS Amount (Rs) 22897000
AS Number WRD005-131-PA-01
TS Amount (Rs) 21000000
TS Number 2020-2021/2019/7768
Total Bill Submitted (Rs) 13029255
Total Bill Paid (Rs) 0
Population Benefitted 20000
Capacity in MLD 0.00
Actual Project Completion Date 21 Jan 2023
Coverage Population benefitted-20000
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB-Project-7-Kolecherry WSS-Zone I-Replacing old 400/350 mm premo/AC pipe from Kothery GLtank to Vayanthode Jn. with 400 mm DI pipe Mattannur PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Mar 2023 work completed and final bill submitted Mattannur WS Sn
01 Mar 2023 work completed and final bill submitted Mattannur WS Sn
25 Feb 2023 work completed and bill under preparation Mattannur WS Sn
20 Feb 2023 pipe laying work completed,PWD road reformation remaining Mattannur WS Sn
09 Feb 2023 pipe laying work completed,PWD road reformation remaining Mattannur WS Sn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/03/2022
Scheduled date of Completion of the Project 15 Sep 2022
Expected date of Completion 15/09/2022

Processing Dates

AS Date 18 Jan 2019
TS Date 25 Feb 2021

Other details

Project Officers View