| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Mar 2021 | Pipe line extension and FHTC works in progress | Kottarakkara PH Dn EE | |
| 12 Mar 2021 | Work in progress | Kottarakkara PH Dn EE | |
| 04 Mar 2021 | pipe line extension work progressing. 51 FHTC provided | Kottarakkara PH Dn EE | |
| 28 Feb 2021 | pipe line extension and providing FHTC work in progress | Kottarakkara PH Dn EE | |
| 23 Feb 2021 | work in progress | Kottarakkara PH Dn EE | |
| 22 Feb 2021 | Work in progress | Kottarakkara PH Dn EE | |
| 13 Feb 2021 | Work in progress | Kottarakkara PH Dn EE | |
| 07 Feb 2021 | Work in progress | Kottarakkara PH Dn EE | |
| 27 Jan 2021 | Agreement executed | Kottarakkara PH Dn EE | |
| 25 Nov 2020 | Extended up to 27/11/2020. | Kottarakkara PH Dn EE |