| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 May 2022 | 36% completed | Kottarakkara PH Dn EE | |
| 04 May 2022 | 2552 FHTC Completed. Pipelaying work also in progress | Kottarakkara PH Dn EE | |
| 06 Mar 2022 | 2250 fhtc completed and pipelaying work is in progress | Kottarakkara PH Dn EE | |
| 28 Feb 2022 | 2119 FHTC Completed and work is in progress | Kottarakkara PH Dn EE | |
| 04 Feb 2022 | 33% completed | Kottarakkara PH Dn EE | |
| 27 Dec 2021 | Pipe line extension works and providing FHTC are in progress | Kottarakkara PH Dn EE | |
| 14 Jul 2021 | Pipe line extension works and providing FHTC are in progress | Kottarakkara PH Dn EE | |
| 06 Jul 2021 | Pipe line extension works and providing FHTC are in progress | Kottarakkara PH Dn EE | |
| 12 Jun 2021 | 587 FHTC Completed | Kottarakkara PH Dn EE | |