Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Feb 2022 | Plastering completed. Electrical work going on. About 30 % work completed. | Thiruvananthapuram QC AE 1 | |
25 Jan 2022 | Plastering going on.About 25% work completed. | Thiruvananthapuram QC AE 1 | |
20 Jan 2022 | Brick work completed,slab casted.About 20% work completed. | Thiruvananthapuram QC AE 1 | |
12 Jan 2022 | Brick work going on About 15 % work completed. | Thiruvananthapuram QC AE 1 | |
06 Jan 2022 | Clearing the site going on. About 5% work completed. | Thiruvananthapuram QC AE 1 |